top of page

Projects

High voltage towers with sky background..jpg

UKPN ED1SON Capital Programme

2021- Present

Working with UKPN and the ED1SON Alliance partners to deliver Load and Generation customer connections across the 11kV-132kV network. This  included the project management of new distributed Generation connections under the ENA G99 recommendations and new Data Centre connections up to 150MVA.

Crane.jpg

Hinkley Point C Nuclear Power Station
Shurton 400kV

2020-Present

Working with Omnia Projects & Linxon as the Principal Contractor Temporary Works Co-ordinator for the new 400kV Shurton substation at Hinckley Point C nuclear power station.

IMG_2606.JPG

National Grid 132kV - 400kV Network

2019-2021

Working with Omnia projects as client representative for National Grid's asset replacement and refurbishment scheme.
This consisted of circuit breakers, current transformers, voltage transformers, disconnectors and earth switches.

cc.jpg

Isle of Grain LNG

2019

Woking with Omnia Project and Siemens as Temporary Works Co-ordinator for the Isle of Grain cable and switchgear replacement for Grid Transformer 2.

IMG_1694.jpeg

National Grid 132kV - 400kV Network

2017-2018

Appointed by Omnia Projects to undertake the project management of asset replacements and asset refurbishments for Omexom Power Solutions on the National Grid primary equipment framework. 

Management of 18 circuit breakers, 4 current transformer, 3 voltage transformers and 21 bay refurbishments. 

IMG_0359.JPG

Hendon 132kV substation

Principal Contractor site management

2016

We undertook the Principal Contractor site management of a new Network Rail connection into existing GIS switchgear.

IMG_0199.JPG

Dudgeon Onshore Cable Project

Principle Contractor Site Managment

2016

Providing site management support to the existing management team to ensure timely delivery of the cable installation to Necton substation.

IMG_0835.JPG

Elstree 132kV Substation

Principal Contractor Site Management

2015 - 2017

We undertook the site management of 132kV circuit transfers from the existing AIS substation to the new GIS switchgear.

IMG_1496.JPG

Limeburner Lane 132kV GIS substation

2014

Provision of labour to supervise the electrical installation of a new GIS substation in central London.

IMG_0096.JPG

Earlham & Rayleigh GIS builds

2010 - 2013

Provision of labour for the mechanical and electrical installation of new 132kV GIS installations, including associated works at remote ends.

bottom of page